IMPOUNDMENT & INTAKE CONSTRUCTION
Construction on the Bel Air Impoundment began in July 2017.
Â
Impoundment
Installation of the impoundment's geomembrane liner began in July 2018.
Panoramic View (as of January 29, 2018)
Allan Myers, the impoundment contractor, is currently working on the riser structure. We expect concrete work will continue on the tower through January 2018. The east and west berms of the impoundment were topped out in November 2017. Top soiling of the exterior east and west berms has been completed.
Â
Intake
The new Winters Run intake and gabions were installed in February 2018.
   Â
A view of the source of Bel Air's water, Winters Run, after the removal of the cofferdam (February 2018).
The intake contractor, Bowen Engineering, continues work on the new Winters Run Raw Water Pump Station.
Â
Construction Timeline
Â