IMPOUNDMENT & INTAKE CONSTRUCTION

Construction on the Bel Air Impoundment began in July 2017.

 

3_1DA8B8

Impoundment

Installation of the impoundment's geomembrane liner began in July 2018.

Liner_installation_0718


Panoramic View (as of January 29, 2018)
Allan Myers, the impoundment contractor, is currently working on the riser structure. We expect concrete work will continue on the tower through January 2018. The east and west berms of the impoundment were topped out in November 2017. Top soiling of the exterior east and west berms has been completed.

  Adobe Spark

Intake

The new Winters Run intake and gabions were installed in February 2018.

    New intake and gabion

A view of the source of Bel Air's water, Winters Run, after the removal of the cofferdam (February 2018).

The intake contractor, Bowen Engineering, continues work on the new Winters Run Raw Water Pump Station.

Winters Run cofferdam removed636564608794160767

 

Construction Timeline

Construction timeline

Â